NO-FROST
CROSS 4-DOOR WITH INVERTER COMPRESSOR
CROSS 4-DOOR WITH NORMAL COMPRESSOR
TOP MOUNT WITH INVERTER COMPRESSOR
TOP MOUNT WITH NORMAL COMPRESSOR
TOP MOUNT WITH NORMAL COMPRESSOR
(US Style)
FRENCH 4-DOOR WITH INVERTER COMPRESSOR
FRENCH 4-DOOR WITH NORMAL COMPRESSOR
COMBI WITH NORMAL COMPRESSOR
COMBI WITH INVERTER COMPRESSOR
COMBI WITH NORMAL COMPRESSOR E-DAMPER
SIDE BY SIDE WITH INVERTER COMPRESSOR
SIDE BY SIDE WITH NORMAL COMPRESSOR
SINGLE-DOOR FREEZER
(EU Style)
SINGLE-DOOR FREEZER
(US Style)
SINGLE-DOOR LARDER
(EU Style)
DEFROST
COMBI
TOP MOUNT
CHEST FREEZER
SINGLE-DOOR FRIDGE
SINGLE-DOOR FREEZER
SINGLE-DOOR LARDER
BUILT-IN COMBI
BUILT-IN TOP MOUNT
BUILT-IN ELECTRONIC SINGLE-DOOR LARDER
BUILT-IN ELECTRONIC SINGLE-DOOR FRIDGE
BUILT-IN MECHANIC SINGLE-DOOR LARDER
BUILT-IN MECHANIC SINGLE-DOOR FRIDGE
FROST FREE
COMBI WITH INVERTER COMPRESSOR
COMBI WITH NORMAL COMPRESSOR
SUPPORT
LOG-OUT
CHECK AND TEST 1
PROCEDURE 1
Step 1
Pull upwards to remove inverter box.
Step 2
Disconnect terminals.
Step 3
Disconnect power cord.
Step 4
Disconnect earthing wires.
PROCEDURE 2
CHECK AND TEST 2
DIAGNOSIS 2
PROCEDURE 3
Step 1
Pull upwards to remove
inverter box.
Step 2
Disconnect terminals.
Step 3
Disconnect power cord.
Step 4
Disconnect earthing wires.
Step 5
Discharge refrigerant. Cut off the charging tube with pliers.
Step 6
Release all refrigerant toward the exhaust vent.
Step 7
Cut off exhaust pipe to check whether oil is being ejected from compressor.
Step 8
Unscrew nut of compressor.
Step 9
Install a new compressor and tighten nuts onto compressor.
Step 10
Braze the joints of suction and exhaust pipes.
Step 11
Re-braze a copper tube onto processing tube of compressor.
To get more details on brazing requirements, please go to
10.4 Annex B1
.
PROCEDURE 4
Step 1
Clean paint off of brazed joint of drying-filter.
Step 2
Cut off drying-filter.
Step 3
Cut off capillary and remove the cut end by shaking.
Step 4
Braze on a new dryingfilter.
Step 5
Inject nitrogen (1.57Mpa) through quick connector into pipe for at least
3 min to blow remaining refrigerant away.
Step 6
Add quick connector onto processing pipe of drying-filter.
Step 7
Perform leakage test on brazed joints of dryingfilter and compressor processing pipe.
Step 8
Vacuum and recharge. Please get more details of vacuuming and gascharging requirements on
10.5 Annex B2
.
Step 9
Block processing pipe twice by locking pliers.
Step 10
Leave locking pliers on the second block and cut off the rest pipe by shaking.
Step 11
Braze the ends and remove the pliers.
CHECK AND TEST 3
DIAGNOSIS 3