CHECK AND TEST 1
Check reworking record.
Check to see if compressor running ratio is close to 100%.
DIAGNOSIS 1
Discharge refrigerant: use pliers to cut off charging tube.
Discharge all refrigerant toward the exhaust vent.
Melt brazing material with flame and pull processing tube out using a pair of pliers.
CHECK AND TEST 2
DIAGNOSIS 2
PROCEDURE 2
Clean paint off of brazed joint.
Cut off brazed joint with leakage.
Use a bigger copper tube to connect 2 ends of brazed joint.
Inject nitrogen at 1.57Mpa through quick connector into pipe and use soapy water to perform leakage test again;
DIAGNOSIS 3
CHECK AND TEST 3
Weld a piezometer onto processing tube of compressor.
Charge nitrogen of 1.57Mpa through quick connector into pipe.
Do leakage test on brazing points and piezometer.
DIAGNOSIS 4
CHECK AND TEST 3
Give the system 1.57Mpa Nitrogen, and then observe if there is rust and/or spotted holes on pipes of compressor niche and evaporator.
If it seems like there is a hole there, apply soapy water to the rusty area to check.
DIAGNOSIS 5
PROCEDURE 3
Clean paint off of brazed joint of drying filter.
Cut off the drying-filter.
Add quick connector onto processing pipe of drying-filter.
Do leakage test on brazed joints of drying- filter and processing pipe on compressor.
Vacuum and recharge. Please get more details of vacuuming and gas- charging requirements, go to Annex-B2
Block processing pipe twice by locking pliers.
Leave locked pliers attached to second block and shake to cut off the remaining pipe.
Braze the ends and remove the pliers.
DIAGNOSIS 6