DIAGNOSIS 1
PROCEDURE 1
Pull upwards to remove inverter box.
Disconnect terminals.
Disconnect power cord.
Disconnect earthing wires.
PROCEDURE 2
DIAGNOSIS 2
PROCEDURE 3
Discharge refrigerant. Cut off the charging tube with pliers.
Release all refrigerant toward the exhaust vent.
Cut off exhaust pipe and suction pipe.
Unscrew nut of compressor.
Install a new compressor and tighten nuts onto compressor.
Braze the joints of suction and exhausting pipes.
PROCEDURE 4
Re-braze a copper tube onto compressor processing tube.
Click below link to get more details of brazing requirements, go to ANNEX B1
Clean paint off of brazed joint of drying-filter.
Cut off drying-filter.
Cut off capillary and shake to remove the cut end.
Braze on a new drying-filter.
Inject nitrogen (1.57Mpa)
through quick connector
into pipe for at least
3 min toblowremaining
refrigerant away.
Add quick connector onto processing pipe of drying-filter.
Perform leakage test on brazed joints of drying- filter and compressor processing pipe.
Vacuum and recharge.
Please get more details of vacuuming and gas- charging requirements go to ANNEX B1
Block processing pipe twice with locking pliers.
Leave locking pliers on the second block and cut off the rest of the pipe by shaking.
Braze the ends and remove the pliers.
DIAGNOSIS 3